top of page
Stock photo of bike tires

Construction

Construction Information

Construction Schedule
Work on all corridors will begin on a staggered schedule, listed below. Work will take place intermittently on each corridor as weather permits. Work will pause during special events as needed. 
Proposed schedule (weather permitting):

  • September 21, 2026: Begin work on Virginia St. corridor

  • Fall 2026: Begin work on Evans Ave./Lake St./Sinclair St. corridor

  • Fall 2026: Begin work on Vine St. corridor

  • Early 2027: Resume work on Virginia St. corridor

  • Summer 2027: Begin work on 5th St. corridor

  • Completion anticipated in summer 2027
     

Work Hours

  • Normal working hours: 7 a.m. - 7 p.m.

  • Intermittent night work anticipated near I-80 between 9 p.m. and 5:30 a.m.

​

Construction Update & Traffic Impacts

Sinclair Street Construction Begins October 19

With Vine Street work paused until later this fall, crews will begin improvements along the Evans Avenue/Lake Street/Sinclair Street corridor on Monday, October 19. Work will start at the Sinclair Street/Moran Street intersection and progress north.

 

During construction, Sinclair Street between Thoma Street and Stewart Street will be open only for access to residences and businesses. Through traffic will be detoured to Center Street or Holcomb Avenue. The Sinclair Street/Moran Street intersection may require a full closure during this work.

 

Please allow extra travel time, follow posted detour signs, and slow down near crews and equipment.

Sinclair Map (1).png
bottom of page